The Local Democracy, Economic Development and Construction Act 2009 finally came into force on the 1 st October 2011; so, by now, it should be on the radar of everybody contracting within the construction industry, whether employer, contractor or sub-contractor.
The Construction Act 2009 makes a number of changes to the operation of construction contracts; including important amendments to the payment provisions set out in sections 110 and 111 of the Housing Grants, Construction and Regeneration Act 1996.
Key Features:-
Points to Remember:-
Guidance for Payers:-
a) The default pay period under the Scheme for Construction Contracts is 28 days, therefore, a valuation, notice and payment will be required on a monthly basis unless an alternative period is agreed;
b) The default Payment Due Date under the Scheme for Construction Contracts is 7 days from the end of the pay period. The relevant Notice must be given within 5 days of the Payment Due Date.
c) The default final date for payment under the Scheme for Construction Contracts is 17 days from the Payment Due Date. The default Prescribed Period is 7 days.
It is not necessary for the contract to require notices to be provided by the Payer; therefore, it may be appropriate in some circumstances for the Payee to be required to do so. Alternatively, the Payee can be required to provide a notification of the sum it considers to be due, prior to the date the Payer Notice must be given.
A Notice to Pay Less must value the sum due for completed work at the date the notice is served (rather than on the Payment Due Date of the payment notice). This means that account must be taken of any Payment Due Dates that have subsequently passed by the time the Notice to Pay Less is served. If no further Payment Due Dates have passed, then the relevant sum will be that due at the Payment Due Date of the Payment Notice. The Notice to Pay Less will be invalid if the wrong period is valued.
Guidance for Payees:-
Unless the contract prevents it, the issue of a section 110A (3) compliant notice prior to the date the Payer Notice must be given, will ensure that the Payer is required to make a payment by the final date, regardless of whether a Payer Notice is provided.
a) The default pay period under the Scheme for Construction Contracts is 28 days, therefore, a valuation, notice and payment will be required on a monthly basis unless an alternative period is agreed;
b) The default Payment Due Date under the Scheme for Construction Contracts is 7 days from the end of the pay period. The relevant Notice must be given within 5 days of the Payment Due Date.
If you are concerned or want to learn how ORJ Solicitors can help you and your Construction business – Please contact Mike Smyth on mike.smyth@orj.co.uk or call him on 01785 223410. To view our website please go to Construction Adjudication